The Portland Bureau of Transportation (PBOT) has contracted with Dirt & Aggregate Interchange for preventive maintenance and rehabilitation of North Vancouver between Russell and Monroe. Work includes a 3” grind and 3” asphalt pavement overlay, digouts in the roadway to repair failed areas, and re-building several sidewalk corners that do not meet ADA standards. The sequence of work will generally be:
- Grinding
- Digouts and corner repair
- Paving
- Striping
Schedule: Work is expected to start the week of May 12th and last through June.
Work Hours: Plan for road construction from 7:00am to 6:00pm M-F
Traffic: No detours are planned at this time, although expect delays. Use alternate routes to avoid congestion. Emergency access will be provided at all times. Flaggers will be on site as necessary. Be aware that grinding and paving does limit access for a period of time.
On-Street parking will not be allowed on Vancouver during construction. Parking is
removed to facilitate the work and to accommodate traffic staging. Please watch for signs.
Parking will be available on side streets.
For more information contact: Todd Liles, Construction Manager, City of Portland, 503-823-6992, Todd.Liles@Portlandoregon.gov.