Eliot Sewer and Stormwater Project Update

Waterline Relocation Work Schedule Update

The Water Bureau, in coordination with Environmental Services, has completed connecting recently relocated water lines in the project area. Additional work by the Water Bureau may occur in the project area if needed.  The Water Bureau will notify residents and business of any temporary disruption to water service.

Continue reading Eliot Sewer and Stormwater Project Update

Advertisements

Eliot Sewer and Stormwater Project Update

Waterline Relocation Work Schedule

This week, the Water Bureau plans to connect recently relocated water lines on Williams Avenue between Sacramento and Tillamook Streets.

The Water Bureau will notify neighbors of any disruption in water service.  If you have questions or concerns, please contact Nate Burton, Public Works Supervisor for the Water Bureau, at 503-823-1843

Continue reading Eliot Sewer and Stormwater Project Update

Eliot Sewer and Stormwater Project Update

Waterline Relocation Work

Work to replace and relocate waterlines that will conflict with sewer and stormwater construction will begin again in June. After completing waterline relocation work, the Water Bureau will perform a series of quality control tests and may identify the need for additional work.

Continue reading Eliot Sewer and Stormwater Project Update

Eliot Sewer and Stormwater Project Update

Environmental Services is coordinating with the Water Bureau to relocate waterlines that will conflict with sewer and stormwater construction in the Eliot neighborhood. Crews were scheduled to begin in mid- December 2017 and continue relocation work through the end of February 2018. The map shows where crews will be working each month. This schedule may change due variables, including conditions underground, weather, subcontractor schedules and availability of materials.

Continue reading Eliot Sewer and Stormwater Project Update